How Much Does Dozer Work Cost per Hour in Mississippi?
Bulldozer work in Mississippi ran $66 to $130 an hour in MSU Extension’s custom-rate survey, with an average of $101.50. One national cost guide prices a bulldozer or excavator with an operator at $1,200 to $2,500 a day. We are based in Waynesboro in Wayne County and offer dozer services across southeast Mississippi and southwest Alabama.
These are market numbers, not our price list. The MSU figure rests on only 2 responses, and it reflects farm-to-farm custom work, not contractor pricing. Over an 8-hour day, the national day rate works out to about $150 to $312 an hour. Where a job lands depends on the machine, the trailer move and the ground.
What do published rates say a dozer costs?
Dozer prices get published by the hour, by the day and by the acre. MSU Extension surveyed producers across the state in spring and summer 2024 for its custom rates. A national cost guide and an equipment rental marketplace show what hired and rented dozers run.
| What is priced | Market range | Where the number comes from |
|---|---|---|
| Bulldozer work, per hour | $66 to $130, average $101.50 | MSU Extension custom-rate survey, 2 responses |
| Bulldozer work, per acre | $110 to $1,600, average $855 | MSU Extension custom-rate survey, 2 responses |
| Bulldozer or excavator with an operator, per day | $1,200 to $2,500 | A national cost guide |
| Mobilization fee, where a company charges one | $150 to $300 | A national cost guide for clearing work |
| Dozer rental, machine only, per day | $500 to $1,500 | An equipment rental marketplace |
| Operator wages, if you rent and hire one | $300 to $500 a day | An equipment rental marketplace |
| Fuel for a rented dozer | $140 to $1,000 or more a day, by size | An equipment rental marketplace |
| Round-trip delivery, dozer under 20,000 pounds | $300 to $600 | An equipment rental marketplace |
| Round-trip delivery, dozer of 40,000 to 80,000 pounds | $1,000 to $2,000 or more | An equipment rental marketplace |
A rental covers the machine. In the marketplace’s math, the renter also pays for fuel, delivery and an operator if they hire one.
What drives the hourly rate for dozer work?
Machine size. Bigger dozers cost more to rent and more to fuel. The rental marketplace says a 15,000-pound dozer costs 2 to 5 times less per day than an 80,000-pound one.
The attachment. A dozer can work with the blade, a root rake or a shear. Each fits a different part of the job. Ask whether the rate changes when the attachment does.
Operator pay. The national guide’s day rate includes an operator. If you rent instead, the rental marketplace puts operator wages at $300 to $500 a day.
The trailer move. A dozer travels to the job on a trailer, and the trip has a cost. A national cost guide for clearing work says some companies charge a $150 to $300 mobilization fee for setup. In the rental marketplace’s figures, delivery climbs with the dozer’s weight.
Minimums. On a short job, the trailer move gets spread over fewer hours. Ask whether the quote carries a minimum charge, and what it covers.
The markup. The MSU survey points to earlier reports on custom work. Those suggested a markup of 20 to 40 percent above the cost of operation. It also notes that custom rates are often negotiable.
Should you pay by the hour, by the job or by the acre?
Each way of pricing puts slow ground on a different side of the deal. With an hourly rate, a wet or stump-heavy day costs you more. With a price for the whole job, the number is set before the dozer comes off the trailer.
By the acre fits clearing, where the growth sets the pace. In MSU’s survey, bulldozer work per acre ran $110 to $1,600, with an average of $855. With only 2 responses, that range is wide. On raw land, dozer work is part of land clearing, and national guides price that by the acre too. See land clearing cost per acre for those ranges by how thick the growth is.
Job size changes the math. One national cost guide says clearing a single acre costs more per acre than clearing five acres. Once the machines are on the site, that guide says, larger areas go more efficiently.
How much ground can a dozer clear in a day?
It depends on the growth, the stumps and the ground. One equipment rental marketplace figures a small dozer clears about 2 acres of light brush a day. It puts that at about $500 to $700 per acre in equipment costs alone. Thicker growth and stumps slow the pace.
Land that can keep its stumps may not need a dozer at all. See forestry mulching or dozer clearing for how the two compare. An excavator handles the digging. That side is excavation and dirt work, and our post on excavation and dirt work cost covers its ranges.
What slows dozer work in Wayne County?
Slow ground shows up on an hourly bill. Here, the clay and the rain set much of the pace.
Red clay. Lorman soils are common in Wayne County. NRCS describes them as very slowly permeable soils formed in clayey and silty sediments. After a rain, wet clay slows the work. The ridges drain better: Smithdale, the county’s most common soil, is very deep and well drained on ridge tops and hill slopes.
Creek bottoms. Bibb soils sit in the creek bottoms. NRCS puts their water table within 8 inches of the surface for 6 to 11 months a year. They flood frequently unless protected.
The wet months. NOAA’s climate normals put Waynesboro at about 60 inches of rain a year. Rain runs heaviest from December through March. October has the lowest normal, at 3.55 inches. Dozer work on clay and in the bottoms goes best in a dry spell.
What should a written dozer quote spell out?
A written quote lets you hold two bids side by side. Ask for one that spells out:
- How the price is set: by the hour, the day, the acre or the whole job.
- The machine and the attachment: the blade, a root rake or a shear.
- The trailer move or mobilization fee, on its own line.
- Any minimum charge, and what it covers.
- Whether fuel is part of the rate.
- Where the stumps and brush go.
- What the ground looks like when the dozer leaves.
- How rain days change the schedule.
How do you get a price for your own dozer work?
Published rates show the market. Your land sets the actual price. See how our dozer services handle clearing, pads and roads. For a new house, site preparation takes a raw lot to a finished pad.
We look at the site, or you send photos and a pin, and we put the quote in writing. Call or text (601) 410-5339.